Owner | Duration |
---|---|
Tourism Development and Investment Company (TDIC) | 2008-2010 |
Permanent diversion of 1200m strech of the 150m wide Eastern Mangroves Channel, including sheetpile double cofferdams, dewatering, rock revetment, construction of quay wall and floating marina system
Design & construction of berth Marina for Vessels from 14m to 160m, approx area of 15,374m2,
Construction of various piers, viewing platforms and floating berth for Yas Island Resort
Design and construction of Marina Restaurant:
Design, supply, install precast slabs and related concrete works