BOROUGE 3 - OFFSITE & UTILITIY



Owner Duration
Borouge 2011-2012

Design, engineering and construction of 4 number 3.0 m diameter submarine sea water intake pipelines including dredging, stringing, sub-sea installation and backfilling. Approximately 15km of intake pipelines was installed utilising float and sink methodology.