Owner | Duration |
---|---|
Empower | 2007 - 2009 |
Supply, installation, testing and commissioning of a 26km District Cooling Distribution Network including valve chambers at the site of the City of Arabia, Dubai
Construction of Chiller water pipe network of length 5.6 Km to deliver chilled water from the existing Semi-Permanent Plant in Dubiotech
Trench Excavation, Supply & Laying of Pre-insulated pipes including fittings, backfilling of trench & testing and commissioning
Construction of Chilled Water Piping Network expansion of approx. 5 Km plotted into four sections for two phases at DLRC and IMPZ including Tie in and Civil Works