| Owner | Duration |
|---|---|
| Empower | 2007 - 2009 |
Supply, installation, testing and commissioning of a 26km District Cooling Distribution Network including valve chambers at the site of the City of Arabia, Dubai
Trench Excavation, Supply & Laying of Pre-insulated pipes including fittings, backfilling of trench & testing and commissioning
Construction of Chilled Water Piping Network expansion of approx. 5 Km plotted into four sections for two phases at DLRC and IMPZ including Tie in and Civil Works
Construction of CHW Network of approx. 4.6 Km to serve chilled water to the plots at DHCC to Jadaf DHCC II- Phase 2 with Tie in Connections