Owner | Duration |
---|---|
EMPOWER | 2016 - 2017 |
Scope includes Construction, testing and commissioning of a 3Km chilled water supply and return network at Blue Water Island including Hot tapping works, micro tunnelling, valve chambers, draw pits and Tie-ins at ETS rooms.
There are a number of complex elements to this project, one of which being the installation of the network within an existing breakwater which requires the removal and reinstatement of rock armour within the surf zone. In addition, the drive and receive pits associated with the micro tunnelling operation required careful design and planning as they were 20m in depth, below the sea-bed. Secant piles were utilized to construct the pits to ensure that they were adequately sealed, the pits were then de-watered and excavated to final invert level ready to receive the micro tunnelling equipment.
Construction of Chilled Water Piping Network expansion of approx. 5 Km plotted into four sections for two phases at DLRC and IMPZ including Tie in and Civil Works
Construction of CHW Network of approx. 4.6 Km to serve chilled water to the plots at DHCC to Jadaf DHCC II- Phase 2 with Tie in Connections
Construction of Chiller water pipe network of length 5.6 Km to deliver chilled water from the existing Semi-Permanent Plant in Dubiotech