Owner | Duration |
---|---|
EMDAD Aviation Fuel Storage FZCO | 2014-2015 |
Extension of EMDAD Jet fuel pipeline from Berth 5 to Berth 7 and associated works including supply & installation of Marine Loading Arms complete with electrical & Instrumentation Works.
Scope includes Supply, Installation, Hydro-testing, Flushing and Commissioning of a Jet Fuel Hydrant Piping System of approximately 2km long ...
Scope includes Supply, Installation, testing and commissioning of Firefighting systems as well as the construction of new Fire Water Storage Tanks, Fire/Foam Systems, F & G Detection and Alarm System...
Supply, installation, hydro testing, flushing and commissioning of a Jet Fuel Line Hydrant Piping System approximately 2km in length...