Owner | Duration |
---|---|
EMPOWER | 2018-2019 |
Construction of Chiller water pipe network of length 5.6 Km with Tie in to the existing pipe network to deliver chilled water from the existing Semi-Permanent Plant in Dubiotech Development to a different plot, and associated works including removal and disposal of road material over trenches ,Excavation, backfilling & reinstatement of trenches
Construction of Chilled Water Piping Network expansion of approx. 5 Km plotted into four sections for two phases at DLRC and IMPZ including Tie in and Civil Works
Construction of CHW Network of approx. 4.6 Km to serve chilled water to the plots at DHCC to Jadaf DHCC II- Phase 2 with Tie in Connections
Trench Excavation, Supply & Laying of Pre-insulated pipes including fittings, backfilling of trench & testing and commissioning