Owner | Duration |
---|---|
Empower | 2005-2007 |
Supply, installation, testing and commissioning and road reinstatement works for a chilled water network approximately 9 Km in length, including valve chambers and draw pits. This project was executed in a brownfield environment where traffic management and the protection of existing services created serious logistical challenges.
Construction of CHW Network of approx. 4.6 Km to serve chilled water to the plots at DHCC to Jadaf DHCC II- Phase 2 with Tie in Connections
Construction of Chiller water pipe network of length 5.6 Km to deliver chilled water from the existing Semi-Permanent Plant in Dubiotech
Trench Excavation, Supply & Laying of Pre-insulated pipes including fittings, backfilling of trench & testing and commissioning